KESTWICK BUILT
DK
The Board
Wilston QLD, Granny flat, 1 bed studio

Minh & Lan Nguyen

$142K
plus $6,200 signed variations
keys in 5 weeks
Paid to date
$71K
50% of contract
Next claim
$28K
Lockup claim, on lockup sign-off
Forecast margin
21.9%
22.0% quoted
Supervisor
Mick Daly
site lead
The stages
Slab
Brenlow Concreting, signed off
Frame
Ardlow Carpentry, signed off
Roof
Larrow Roofing, signed off
Lockup
in progress, 50% through
Fixout
3 wk planned
Handover
1 wk planned
The build, live
Now13 Oct
The money
Deposit5% of contract$7,100Paid
Slab claim20% of contract$28,400Paid
Frame claim25% of contract$35,500Paid
Lockup claim20% of contract$28,400Upcoming
Fixout claim20% of contract$28,400Upcoming
Handover claim10% of contract$14,200Upcoming
Paid to date$71,000
Variations
Hamptons facade upgrade$6,200
Signed
Stone benchtop upgrade$3,400
Draft
Lockup checklist
2/4
Windows in
External doors hung
Wrap complete
Lock changed to site set
Next trade in

Cabinetmaker: Dunmere Interiors

Starts Tue. Plans and induction attached.

Confirmed
THIS WEEK

Lockup underway

Glazier on site this week. On schedule for handover in 5 weeks.

1 WK AGO

Roof complete

Roof is on. Lockup is next, windows and doors.

2 WK AGO

Frame complete

Walls and trusses are up. You can walk the rooms now.

4 WK AGO

Slab complete

Slab poured and cured. Frames arrive next week.

Sent automatically at every stage sign-off, here and by text. The where-is-my-build call does not exist.