The Board
The Gap QLD, Custom home, single storey

James & Ada Okafor

$780K
plus $1,950 signed variations
keys in 13 weeks
Paid to date
$195K
25% of contract
Next claim
$195K
Frame claim, on frame sign-off
Forecast margin
19.4%
19.5% quoted
Supervisor
Jo Harmer
site lead
The stages
Slab
Corvale Concrete, signed off
Frame
in progress, 67% through
Roof
2 wk planned
Lockup
3 wk planned
Fixout
5 wk planned
Handover
2 wk planned
The build, live
Now13 Oct
The money
Deposit5% of contract$39,000Paid
Slab claim20% of contract$156,000Paid
Frame claim25% of contract$195,000Upcoming
Lockup claim20% of contract$156,000Upcoming
Fixout claim20% of contract$156,000Upcoming
Handover claim10% of contract$78,000Upcoming
Paid to date$195,000
Variations
Skylight to living$1,950
Signed
Frame checklist
3/5
Frames delivered
Wall frames stood
Trusses craned
Tie-down complete
Frame inspection
Next trade in

Roofer: Wexley Roofing

Starts Thu. Plans and induction attached.

Unconfirmed
THIS WEEK

Frame underway

Carpenter on site this week. On schedule for handover in 13 weeks.

2 WK AGO

Slab complete

Slab poured and cured. Frames arrive next week.

Sent automatically at every stage sign-off, here and by text. The where-is-my-build call does not exist.