KESTWICK BUILT
DK
The Board
Stafford QLD, Granny flat, 2 bed

Peter Reid

$176K
plus $2,150 signed variations
keys in 1 weeks
Paid to date
$123K
70% of contract
Next claim
$35K
Fixout claim, invoiced Friday
Forecast margin
22.6%
22.0% quoted
Supervisor
Mick Daly
site lead
The stages
Slab
Brenlow Concreting, signed off
Frame
Hales Framing Co, signed off
Roof
Wexley Roofing, signed off
Lockup
Pellbrook Doors, signed off
Fixout
Tallowmere Cabinets, signed off
Handover
in progress, 0% through
The build, live
Now13 Oct
The money
Deposit5% of contract$8,800Paid
Slab claim20% of contract$35,200Paid
Frame claim25% of contract$44,000Paid
Lockup claim20% of contract$35,200Paid
Fixout claim20% of contract$35,200invoiced Friday
Handover claim10% of contract$17,600Upcoming
Paid to date$123,200
Variations
Extra split system, bed 2$2,150
Signed
Handover checklist
0/4
Practical completion walk
Defects closed
Keys cut
Handover pack printed
Next trade in

QA walkthrough: Kestwick QA

Starts Mon. Plans and induction attached.

Confirmed
THIS WEEK

Handover underway

QA walkthrough on site this week. On schedule for handover in 1 week.

THIS WEEK

Fixout complete

Cabinets, paint and floors are done. Final checks begin.

3 WK AGO

Lockup complete

Windows and doors are in, the build is secure.

5 WK AGO

Roof complete

Roof is on. Lockup is next, windows and doors.

6 WK AGO

Frame complete

Walls and trusses are up. You can walk the rooms now.

8 WK AGO

Slab complete

Slab poured and cured. Frames arrive next week.

Sent automatically at every stage sign-off, here and by text. The where-is-my-build call does not exist.