Morningside QLD, Granny flat studio
Yuki & Ken Tanaka
$128K
plus $2,900 signed variations
keys in 4 weeks
Paid to date
$64K50% of contract
Next claim
$26KLockup claim, invoiced Friday
Forecast margin
23.2%22.0% quoted
Supervisor
Mick Daly
site lead
The stages
Slab
Brenlow Concreting, signed off
Frame
Ardlow Carpentry, signed off
Roof
Wexley Roofing, signed off
Lockup
Tamsworth Glazing, signed off
Fixout
in progress, 0% through
Handover
1 wk planned
The build, live
Now13 Oct
The money
Deposit5% of contract$6,400Paid
Slab claim20% of contract$25,600Paid
Frame claim25% of contract$32,000Paid
Lockup claim20% of contract$25,600invoiced Friday
Fixout claim20% of contract$25,600Upcoming
Handover claim10% of contract$12,800Upcoming
Paid to date$64,000
Variations
Wider rear sliding door$2,900
SignedExtra split system, bed 2$2,150
DraftFixout checklist
0/5Electrical fit-off
Plumbing fit-off
Cabinets installed
Paint complete
Floor coverings
Next trade in
QA walkthrough: Kestwick QA
Starts Mon. Plans and induction attached.
Confirmed
What Yuki sees
Open the homeowner viewTHIS WEEK
Fixout underway
Cabinetmaker on site this week. On schedule for handover in 4 weeks.
THIS WEEK
Lockup complete
Windows and doors are in, the build is secure.
2 WK AGO
Roof complete
Roof is on. Lockup is next, windows and doors.
3 WK AGO
Frame complete
Walls and trusses are up. You can walk the rooms now.
5 WK AGO
Slab complete
Slab poured and cured. Frames arrive next week.
Sent automatically at every stage sign-off, here and by text. The where-is-my-build call does not exist.