Bulimba QLD, Granny flat + carport

Gina & Paul Marchetti

$184K
no variations
keys in 3 weeks
Paid to date
$92K
50% of contract
Next claim
$37K
Lockup claim, invoiced Friday
Forecast margin
19.9%
22.0% quoted
Supervisor
Jo Harmer
site lead
The stages
Slab
Brenlow Concreting, signed off
Frame
Ardlow Carpentry, signed off
Roof
Larrow Roofing, signed off
Lockup
Pellbrook Doors, signed off
Fixout
in progress, 33% through
Handover
1 wk planned
The build, live
Now13 Oct
The money
Deposit5% of contract$9,200Paid
Slab claim20% of contract$36,800Paid
Frame claim25% of contract$46,000Paid
Lockup claim20% of contract$36,800invoiced Friday
Fixout claim20% of contract$36,800Upcoming
Handover claim10% of contract$18,400Upcoming
Paid to date$92,000
Variations

No variations on this job.

Fixout checklist
2/5
Electrical fit-off
Plumbing fit-off
Cabinets installed
Paint complete
Floor coverings
Next trade in

QA walkthrough: Kestwick QA

Starts Thu. Plans and induction attached.

Confirmed
THIS WEEK

Fixout underway

Cabinetmaker on site this week. On schedule for handover in 3 weeks.

1 WK AGO

Lockup complete

Windows and doors are in, the build is secure.

3 WK AGO

Roof complete

Roof is on. Lockup is next, windows and doors.

4 WK AGO

Frame complete

Walls and trusses are up. You can walk the rooms now.

6 WK AGO

Slab complete

Slab poured and cured. Frames arrive next week.

Sent automatically at every stage sign-off, here and by text. The where-is-my-build call does not exist.